Project Controls/Value EngineeringWest Pharmaceutical Production Facility, Offices and Central Utility Plant (Kinston, NC)
STV provided fast-track design-build services for a new high quality, pharmaceutical-grade facility for West Pharmaceutical Services after an explosion devastated its building complex. STV’s construction management services included preparing detailed design documents,
generating contractor interest, leading the pre-qualification and procurement efforts, leading pre-bid meetings, providing cost estimates and scheduling, leading construction completion and coordinating with county and state regulatory agencies. The firm's design and construction strategy restored production capabilities quickly, compressing approximately 18 months of design and construction into just eight months.